Drilling began 3/12/2004 and was completed 4/18/2004.

The Carolina Continental Margin Drilling Program has a prioritized list of drill locations where geologic, stratigraphic, and hydrologic data are needed. The Hope Plantation drill site is one of those locations. The Eastern Earth Surface Process Team will be drilling a deep stratigraphic corehole at this site.

A significant aspect of this particular drilling project will be the collection of continuous core at depth. The first drilling sequence will be conducted using a HQ rod (2 1/2") size drill bit to a targeted depth of about 900 feet. At the 900 ft depth, drilling will be shut down for about a week while the crew exchanges the drill bit for a NQ rod (1 7/8") size drill bit. If time and circumstances permit the drilling may continue the following week; an attempt will be made to drill to basement.

Day Date Activity Photos (1) Run (2) Total Depth
(in ft.)
Aquifer (3) Geologic Unit (4)
These data are provisional, have not been reviewed, and are subject to change.
1 3/8/04
Monday
Drill rig and core recovery equipment packed and loaded          
2 3/9/04
Tuesday
Drill rig and core recovery specialists depart from Reston
Freezing temperatures at drill site; snow possible
Hope Plantation      
3 3/10/04
Wednesday
Set up for drilling Drill rig        
4 3/11/04
Thursday
Obtained clearance to drill at 4:30PM Drill site        
5 3/12/04
Friday
Well was spudded in at 8:00; Drilling began at 8:30 AM Drilling 10 40 Yorktown Confining Unit Chowan River Formation
6 3/13/04
Saturday
Coachman, Bladen, and type section of Donoho Creek geologic units are missing
Unconformity at 114 and 118.3 feet
shelly section 19 120 Beaufort Aquifer unnamed Cretaceous unit
7 3/14/04
Sunday
Reached the top of the Cape Fear Formation at 188 feet
Rain, cold wind
core from Cape Fear 29 200 Upper Cape Fear Confinging Unit Cape Fear Formation
8 3/15/04
Monday
Good core recovery (70ft) - both quality and quantity
More cold drizzlely rain
Drilling in rain 37 270 Upper Cape Fear Aquifer Cape Fear Formation
9 3/16/04
Tuesday
Drilling stopped early due to approaching thunderstorms Core, base of Cape Fear 41 300 Upper Cape Fear Aquifer Cape Fear Formation
10 3/17/04
Wednesday

Cold, damp, drizzle

in non-marine zone IV at 329 ft

loaded core barrel 49 363 Lower Cape Fear Confining Unit Cape Fear Formation
11 3/18/04
Thursday
non-marine zone IV? washing core 55 420 Lower Cape Fear Confining Unit Cape Fear Formation
12 3/19/04
Friday
Ran borehole geophysics in Strat hole   62 490 "Potomac Group" Confining Unit Cape Fear Formation
13 3/20/04
Saturday
Peter Malin visited the site and brought his geophysical seismic device for review Peter Malin 67 540 "Potomac Group" Confining Unit Cape Fear Formation
14 3/21/04
Sunday

Good recovery, lot of core
Early downpour, balmy afternoon

marine zone IV(?) begins at 572 ft

describing core   600 "Potomac Group" Confining Unit Marine Cenomanian
15 3/22/04
Monday
Recovery 93%
Drilling has slowed considerably in these fine uniform clean tight sands
Record low temperatures (24-29°) predicted overnight.
shell cast 78 646.5 "Potomac Group" Confining Unit Marine Cenomanian
16 3/23/04
Tuesday
    82 660 "Potomac Group" Confining Unit Marine Cenomanian
17 3/24/04
Wednesday
Sample show nannofossils - definitely marine
Not drilling deeper; collecting borehole geophysics
changing bit 83 670 "Potomac Group" Confining Unit Marine Cenomanian
18 3/25/04
Thursday
Logging and storing core; securing site securing site        
19 3/26/04
Friday
Obtaining GPS elevation data obtaining elevation        
No drilling from Saturday, 3/27/04, to Wednesday, 3/31/04
20 4/1/04
Thursday
Re-established drill site          
21 4/2/04
Friday
Returned to 470' inside the same drill hole Second round   Rtnd. to 470    
22 4/3/04
Saturday
Re-established hole Logging core 85 680 "Potomac Group" Confining Unit Marine Cenomanian
23 4/4/04
Sunday
70' drilled
Age, range CC9-CC13 (Cenomanian-Turonian)
Preparing slides 93 750 "Potomac Group" Confining Unit Marine Cenomanian
24 4/5/04
Monday
Entered Potomac (lower Cretaceous) at 759 ft Core sample 100 800 "Upper Potomac Group" Aquifer Potomac Group
25 4/6/04
Tuesday
no coring   101 810 "Upper Potomac Group" Aquifer Potomac Group
26 4/7/04
Wednesday
went through a tight clay below the "Upper Potomac" Aquifer Core from aquifer 104 840 "Upper Potomac Group" Aquifer Potomac Group
27 4/8/04
Thursday
collected Strontium samples (ECU) 108 875 "Lower Potomac Group" Aquifer Potomac Group
28 4/9/04
Friday
46 ft drilled; good progress considering depth
cobbles common 878-901 feet
Rescued wildlife 114 921.5 "Potomac Group" silts and clays Potomac Group
29 4/10/04
Saturday
fighting clay Paleosol 118 950 "Potomac Group" silts and clays Potomac Group
30 4/11/04
Sunday
consultation between project geologist, stratigrapher, hydrologist, and paleontologist regarding formation breaks Discussion group 123 973 "Potomac Group" silts and clays Potomac Group
31 4/12/04
Monday
drilling in the rain Borehole geophysics 125 985 "Potomac Group" silts and clays Potomac Group
32 4/13/04
Tuesday
Fossilized root in paleosol zone Fossilized root 131 1021 "Potomac Group" silts and clays Potomac Group
33 4/14/04
Wednesday
spent the day chasing a rock down the borehole The rock 133 1032 Triassic Basin rock Chatham Group
34 4/15/04
Thursday
Recovered the second rock that had been blocking the entrance to the core barrel Second rock 136 1045 Triassic Basin rock Chatham Group
35 4/16/04
Friday
Passed through weathering zone on top of Triassic at 1052ft. collecting logs 140 1063 Triassic Basin rock Chatham Group
36 4/17/04
Saturday
Drove 65 of the 99 boxes of core to NCGS in Raleigh for storage core 144 1090 Triassic Basin rock Chatham Group
37 4/18/04
Sunday
Reached basement discussion 145 1094.5 Triassic Basin rock Chatham Group
38 4/19/04
Monday
the drilling crew is begining the abandonment of the corehole cementing corehole        
39 4/20/04
Tuesday
abandonment continues          
40 4/21/04
Wednesday
site restoration          
 
  6/15/04
Wednesday
returned to site to install piezometer drilling        

1 The complete set of drilling photos are available on the 2004 Hope Plantation Photos Page.

2 Run indicates the cumulative number of runs completed at the end of each day; a run represents the number of times the core barrel has retrieved a core sample

3 Aquifer indicates the deepest aquifer/confining unit reached during the day's drilling; aquifer names are provisional, subject to approval

4 Geologic Unit indicates the deepest geologic unit reached in the day's drilling; these geologic names are provisional and have not yet been reviewed for conformity with the North American Stratigraphic Code.


U.S. Department of the Interior, U.S. Geological Survey
Last update: Saturday, May 7 2005, 11:54:41 AM
URL: http://nc.water.usgs.gov/ccp/2004Hope/drilling.html
Privacy Statement || Disclaimer || Accessibility
Maintainer: North Carolina Web Development Team